Activities
DEMO Design Workshop
★ 1st3-5 July, 2007 @Rokkasho
・What is DEMO?
・DEMO physics
・DEMO Technology and Engineering
・Proposal on DEMO R&D
★ 2nd28-30 January, 2008 @Tokyo
・Road map to DEMO
・Progress in DEMO Design
・Design requirements for DEMO R&D
・Report of DEMO Design Activity
★ 3rd14-16 July, 2008 @ENEA
・R&D on SiC/SiC composites
・Material Engineering for DEMO Blanket
・Design requirements for DEMO R&D
(Neutron multiplier, Tritium breeder)
★ 4th3-5 February, 2009 @Kyoto
・Report of DEMO Design Activity
・MHD equilibrium issues for DEMO
・Divertor physics design issues for DEMO
・System design
★ 5th5-7 October, 2009 @Garching
・ |
Design issues on plasma physics,plasma engineering, magnet and divertor |
・ |
System code |
Technical Coordination Meeting of DEMO Design Activity (TCM)
★ 1st19-20 January, 2011 @Tokyo
・Key design issues on DEMO
・Progress on DEMO R&D activities
・Work plan of HTs
・System code
★ 2nd24-25 May, 2011 @Garching
・DEMO Objectives – WP 2011
・System Code Benchmark
・DDA Project Management Issues
・Key Design Issues (Blanket, divertor, remote maintenance)
★ 3rd1-3 February, 2012 @Tokyo
・ |
System Code Studies |
・ |
Issues with Pulsed Fusion Reactors |
・ |
Key Design Issues (Blanket, divertor,remote maintenance) |
★ 4th4-6 February, 2013@Rokkasho
・ |
Overview of DEMO Design Activities |
・ |
Key Design Issues (Blanket, divertor,remote maintenance, system code,magnet,safety, material) |
・ |
Key Design Issues (Blanket, divertor,remote maintenance) |
★ 5th4-6 February, 2014 @Kyoto
・ |
Overview of DEMO Design Activities |
・ |
Key Design Issues (Blanket, divertor,remote maintenance, system code,magnet,safety, material) |
・ |
Key Design Issues (Blanket, divertor,remote maintenance, system code,magnet,safety, material) |
★ 6th2-3 February, 2015 @Kashiwa
★ 7th1-2 February, 2016@Nagoya
・Plasma design, divertor, first wall
・Blanket, RM and technology
・Safety study, Tritium removal
・Pedestal plasma, ELMs in DEMO
★ 8th7-8 February, 2017@Kyoto
・2nd DDA intermediate report
・Tritium design and Blanket design
★ 9th14-15 February, 2018@Osaka
・ |
Progress of DEMO Design Activities (DDA) during 2017 by JA and EU were reported: Breeding Blanket design, DEMO Physics Basis, Divertor and Power Exhaust, Update on systems code study, Safety, Superconducting Magnet, Remote Maintenance, Plant design, Balance of Plant and Tritium process. |
・ |
DEMO R&D: Progress on JET-ILW PWI analysis and Material Handbook was reported. |
・ |
Discussion on future collaborative activities for the BA DEMO DDA phase II started. |
★ 10th5-6 March, 2019@Naka
・ |
Progress of DDA joint works was reported: (i) Study on shielding, water activation for Breeding blanket, (ii) Tritium permeation for DEMO plant, (iii) Plasma physics: ELM mitigation strategy, (iv) Divertor: comparison of divertor simulations in EU DEMO conditions, (v) System code: Comparison study of the divertor model in EU system code to SONIC., (vi) Magnets: comparison of magnets design. |
・ |
DEMO R&D: Progress on JET-ILW PWI analysis and Material Handbook was reported. The final report schedule of JET-ILW PWI analysis was also proposed. |
・ |
Plan for the DDA final report was proposed and discussed. |
・ |
Topics and Milestones of DEMO DDA in BA Phase II were proposed and discussed. |
Task meeting of DEMO Design Activity
★ 1st30 May-3 June 2011 @Culham
・System code benchmark
・Divertor design
★ 2nd7-18 November, 2011 @Rokkasho
★ 3rd27-28 March, 2012 @Garching
・Critical design issues
(Blanket, divertor, RM, system code, magnet, safety, material)
★ 4th19-26 April, 2012 @Rokkasho, Kashiwa
・Safety
(Blanket, divertor, RM, system code, magnet, safety, material)
★ 5th10-11 July, 2012 @Garching
・Critical design issues
(In-vessel components design,RM,Superconducting magnet)
★ 6th1-3 October, 2012 @Garching
・Critical design issues
(System code, Tritium issues, Safety)
★ 7th15-20 November, 2012 @Tokyo, Rokkasho
・Safety
(Safety requirement, etc.)
★ 8th28 January -1 February, 2013 @Rokkasho
・System code
(Modeling of magnet, shield, DEMO scoping)
★ 9th5-8 March, 2013 @Kashiwa
・Safety
(Various issues on fusion safety)
★ 10th3-4 June, 2013 @Garching
・Critical design issues
(Blanket, divertor, safety and systems code)
★ 11th12-13 September, 2013 @Garching
・Critical design issues
(Blanket, divertor, RM, magnet, systems code)
★ 12th8-11 October, 2013 @Kashiwa
・Safety
(Various issues on fusion safety)
★ 13th10-13 February, 2014 @Kashiwa
・System code
(Physics and cost models, scoping study)
★ 14th4-7 March, 2014 @Kyoto
・Safety
(Miscellaneous safety issues)
★ 15th15-21 March, 2014 @Culham
・Critical design issues
(Divertor, Remote maintenance)
★ 16th24-25 June 2014 @Garching
・Coordination
(Critical design issues (materials, plasma)
★ 17th1-5 September 2014 @Culham
★ 18th27 September 2014 @Barcelona
★ 19th27-31 October 2014 @Rokkasho, Kashiwa
★ 20th24-26 November 2014 @Garching
・DDA Intermediate Design Report
★ 21st16-20 March 2015 @Shin-Kawasaki
★ 22nd7-8 July 2015 @Garching
・Critical design issues
(Divertor, First wall, Hot cell, Magnets)
★ 23rd31 Aug.-4 Sep. 2015@Rokkasho
★ 24th3-5 Nov.2015@Garching
・Breeding blanket concepts, technical and safety issues
・System codes and blanket design
・Vertical stability
・Balance of plant and design integration
・Recent progress in neutronics and Demo design
・First wall loads and divertor dome
★ 25th8-11 March, 2016@Kyoto
★ 26th21-23 June, 2016@Garching
・Heat & particle load
・Plasma control
・Balance of plant
★ 27th23-25 November, 2016@Garching
・Preparation for 2nd DDA intermediate report
★ 28th20-22 June, 2017@Garching
・ |
Plant system and system engineering |
・ |
In-vessel components, remote maintenance, hot cell concept |
・ |
Physics and divertor |
・ |
Collaborative target during BA-DDA extension (2017-2019) |
★ 29th29-30 November, 2017@Garching
・ |
Progress on blanket concept and material development, core and divertor plasma physics, SC coil design, Plant design and BoP, cost model for DEMO plant. Preparations and Discussions for R&D in BA phase II. |
★ 30th 23-24 April, 2018@Garching
・ |
JA-EU joint works to the final report were proposed, and discussed. |
・ |
Activities for the BA DEMO R&D phase II (2020-2025) were agreed. |
・ |
Discussion on future collaborative activities for the BA DEMO DDA phase II started. |
★ 31th 22-26 October, 2018@Rokkasho
・ |
Dr. James Morris (CCFC) visited in QST, Rokkasho Fusion Institute (Oct. 15-24) for collaboration study to compare divertor parameters between EU system code and 2D simulation. |
★ 32th 19-20 November, 2018@Garching
・ |
Proposals of EU-JA joint works for the DDA final report were agreed to start. |
・ |
Schedule and responsible authors for the DDA final report were agreed. |
・ |
Common topics for the BA DDA Phase II were discussed, and milestones of each topic are summarized until TCM-10 and PC-24. |